§ 30-355. Coordination of construction activities.  


Latest version.
  • All grantees and cable providers are required to cooperate with the city and with each other.

    (1)

    By January 1 of each year, grantees and cable providers shall provide the city with a schedule of their proposed construction activities in, around or that may affect the public rights-of-way.

    (2)

    Each grantee and cable provider shall meet with the city, other grantees and users of the public rights-of-way annually or as determined by the city to schedule and coordinate construction in the public rights-of-way.

    (3)

    All construction locations, activities and schedules shall be coordinated, as ordered by the city engineer, to minimize public inconvenience, disruption or damages.

(Code 2006, § 12.44.33; Ord. No. 1558 , § 1(Exh. A), 2-14-2017)